The progress on the church construction is moving forward partially due to the $12,000 gift
from the Apostles Rwanda Fund. The government several months ago told the
parish that they needed to complete the construction by the end of July or risk
the old building (still out of building conformance) being also closed.
The government has witnessed the progress and is not planning to take any such
action now that the new building is moving forward so well. Praise! Much of the
work is done by members of the congregation - the money is mainly for materials
and some special sub contractors.
Words below from Marcel Sebahire at the Shyogwe Diocese and good
friend of Apostles:
Greetings from Gikomero, your sister church.
We are very excited to share with you about the construction
progress that we have done so far.
1. We have finished elevating the walls: The walls are now
elevated and well finished;
2. We are done with plastering: The inside walls are all
plastered;
3. We have put/installed all doors and windows;
4. We have installed the electrical wires: The rest is to
connect the lambs and connect the church electricity system to the public grid;
5. We have finished digging the toilet pits: We are seeing how
to construct the toilet building;
6. We have done outside finishing activities for all doors and
windows
WHAT IS BEING DONE RIGHT NOW?
1. We are laying stones for pavement with cement
2. We are building the front (altar) and we will continue
with tiling.
3. We are putting metal tubes in the two up-sides of the church
building where the glasses will be installed.